In May of 2015 the WCSD set out to create a committee to discuss the priorities of how the Wappingers Central School District should spend the $5,327,266.00 we have been allocated as part of the Smart Schools Bond Act (SSBA). The SSBA was passed by the voters of New York State in the November of 2014 general election.
The SSBA is now part of the 2014-15 NYS Enacted Budget. (L. 2014, ch. 56, Parts B and C). The Smart Schools Bond Act (SSBA) authorizes the issuance of $2 billion of general obligation bonds to finance improvements in educational technology and building infrastructure, with the end goal of improving learning opportunities for students throughout the state (The Wappingers Portion is once again $5,327,266.00).
New York State has created the Smart Schools Website which includes all of the details about the SSBA.. Included on this site is the SSBA Guidance Document which describes the desire / need for all stakeholders to be included in the decisions our district makes in spending these funds. The SSBA Committee (SSBAC) is one of the requirements outlined in the guidance document, and is a group consisting of parents, community members, teachers, and administrators.
One of the main outcomes of this committee will be to assist in the creation of the “Smart Schools Improvement Plan (SSIP)”, which is a document the district must submit in order to request funding for any projects related to the spending of SSBA money. A district can submit multiple SSIP's to NYSED until all of
A presentation was made at the J Wappingers Board of Education meeting outlining our fifth SSIP for which we will be seeking community input and ultimately NYSED approval. The proposed scope of this plan is to purchase additional display technology to replace aging equipment throughout the district and to replace and upgrade our wireless infrastructure at all ten elementary buildings. A copy of the SSIP can be found here:
Components of our SSIP #5 Submittal
A presentation was made at the J Wappingers Board of Education meeting outlining our fourth SSIP for which we will be seeking community input and ultimately NYSED approval. The proposed scope of this plan is to purchase additional display technology to replace aging equipment throughout the district, install air conditioners and generators in key network closets, to replace and upgrade our wireless infrastructure at Wappingers Jr./Van Wyck, and to install new wireless panic systems throughout the district. A copy of the SSIP can be found here:
Now Amended Updated Wappingers CSD SSIP #4
Original Wappingers CSD SSIP #4
Components of our SSIP #4 Submittal
A presentation was made at the September 26, 2016 Wappingers Board of Education meeting outlining our third SSIP for which we will bee seeking community input and ultimately NYSED approval. The proposed scope of this plan is to purchase additional Chromebook Carts for the elementary buildings as well as additional carts for Wappingers Jr. This plan will also include the purchase of Chromebooks for our elementary teachers to use for curriculum development and planning. Lastly, the plan also requests the purchase of new radio communications systems including handheld radios for the district in order to improve communication in case of an emergency. A copy of the SSIP can be found here:
Components of our SSIP #3 Submittal
Add additional Chrome Carts to our elementary buildings
Improve upon the district's radio capabilities in emergency situations
UPDATE (3.29.2017) - Per the New York State Department of Education, the plans to improve the district's radio capabilities were denied under the pretense that the radios and related equipment did not meet the parameters set forth by the Smart Schools office.
UPDATE (4.5.2017) - During the Board of Education meeting on April 3, 2017 the board passed a resolution relating to SSBA Plan #3 which stated:
WHEREAS the Board of Education approved the Smart Schools Bond Act Implementation Plan #3 on November 7, 2016; and
WHEREAS the Office of Educational Management Services of the New York State Education Department has deemed that the radios requested in the plan are not consistent with the guidance for High-Tech Security projects under the Smart Schools Bond Act and therefore are not eligible for funding under the Smart Schools Bond Act;
NOW THEREFORE BE IT RESOLVED, that the Wappingers Board of Education hereby approves the Smart Schools Bond Act Implementation Plan #3, as revised.
The revised plan is as follows: Wappingers CSD SSIP #3 - REVISED
A presentation was made at the 6/20/2016 Wappingers Board of Education Meeting outlining our second SSIP for which we will be seeking community input and ultimately NYSED approval. The proposed scope of this plan is to add visitor vestibules to 13 of our school buildings which do not currently have one (Wappingers Jr. HS is the only school which has a vestibule). A copy of this SSIP plan can be found here:
Wappingers CSD SSIP #2
To compliment this plan, please see the following pdf that shows the conceptual foot print for the new vestibules at each school. The design phase of this plan will determine the exact look and feel of each entrance, but that will not be developed until this plan is approved by NYSED.
Wappingers CSD SSIP # 2 Vestibule Footprint
Components of our SSIP #2 Submittal
Adding visitor vestibules to buildings which do not have one.
a) Issue To Be Addressed: Visitor management continues to be a security concern in our schools. The main entrance doors to our schools are still opened far often than necessary so that we may accept packages and visitors into our schools.
b) SSBAC Recommended Solution: Allocate $1,2000,000 (Budgetary figure based on estimates provided by Rhinebeck Architecture and Planning PC) of the SSBA funds to either add vestibules to existing lobbies or to redesign main entrances to accommodate the addition of vestibules to all of our schools (Wappingers Jr. HS already has an adequate vestibule).
Our SSIP Plan # 1 was approved by NYSED on 5/11/2016, As of 9/26/2016 a majority of this work has been completed. We are only waiting on door hardware changes at one of our schools. All interactive panels were installed and operational by the end of the first week of the 2016-2017 school year.
A presentation was made at the 12/14/2015 Wappingers Board of Education Meeting outlining the first SSIP for which we will be seeking community input and ultimately NYSED approval. A copy of this SSIP plan can be found here:
Wappingers CSD SSIP #1 (Uploaded 12/15/2015)
Wappingers CSD SSIP #1 Revised for P&P (Uploaded 2/2/2016)
Components of our SSIP #1 Submittal
Interactive Whiteboards and Displays In Every Classroom:
District Wide Intruder Cores:
SSBA Funding Balance
WCSD Initial Allocation | $5,327,266 |
SSIP #1 (As per draft on 12/15/2015) | $1,450,000 |
SSIP #2 (As per presentation from 6/20/2016) | $1,200,000 |
SSIP #3 (As per presentation from 9/26/2016) | $650,200 |
Private and Parochial Allocation (If $3.1 Million of SSBA is spent on Learning Technology). The balance below does not include this figure subtracted, it is a possible expenditure, but not an actual allocation. | $197,250 |
Private and Parochial Allocation Adjusted (Based on SSIP 1) | $63,120 |
Private and Parochial Allocation Adjusted (Based on SSIP 3) | $29,982 |
Balance of Funds | $1,933,964 |
Balance of Private and Parochial funds (If the district meets the maximum spending criteria in the instructional technology category of the SSBA). This total is subject to change based on district spending priorities in the other categories. |